
PROJECTS
Equaling Helsinki’s electricity consumption
Megatuuli´s projects
Megatuuli is the leading wind farm developer in Finland, with a project portfolio under development of more than 1.000 MW pipeline consisting of about 3000 MW of projects.
Project pipeline of Megatuuli
Tyrinselkä I/Jokioinen (4 WTG) – in operation since 2016
Tyrinselkä II/Ypäjä (3 WTG) – in operation since 2021
Tyrinselkä II/Humppila (1 WTG) – in operation since 2021
Soidinmäki/Saarijärvi (8 WTG) – under construction
Rasakangas/Kurikka (9 WTG) – under construction
Saunamaa/Teuva/Kurikka (8 WTG) – in operation 2021
Suolakangas/Kauhajoki (9 WTG) – in operation 2021
Honkamäki/Vesanto (6 WTG) – permitting ongoing
Sikamäki/Viitasaari (3 WTG) – permitting ongoing
Yli-Olhava/Ii (60 WTG) - land use plan approved Feb 1st 2021
Kalistanneva/Kurikka (27 voimalaa) - under construction
Matkussaari/Kurikka (30 voimalaa) - under construction
Honkamäki/Vesanto (6 voimalaa) – lupaprosessi käynnissä
Sikamäki/Viitasaari (3 voimalaa) – lupaprosessi käynnissä
Ristiharjunkalliot/Teuva (3 voimalaa) - lupaprosessi käynnissä
Yli-Olhava/Ii (50 voimalaa) - land use plan approved 2021, permitting ongoing
Paulakangas/Teuva (9 voimalaa) - land use planning and EIA started 2021
Leppämäki/Pyhäjärvi (6 voimalaa) - land use planning and EIA started 2021
Honkalankangas/Vaala (9 voimalaa) - land use planning and EIA started 2022
Neittävänvaara/Siikalatva (24 voimalaa) - land use planning and EIA started 2022
Lapinsalo/Kiuruvesi (38 voimalaa) - land use planning and EIA started 2022
Lakkasuo/Simo (8 voimalaa) - land use planning and EIA started 2022
Projects in prefeasibility phase about 2000 MW.
Contact us
Tyrinselkä
Tyrinselkä wind farm – The most efficient wind farm in Finland
The first realized wind farm project Tyrinselkä I is located in Jokioinen municipality. The project development started in 2011, construction started in 2015 and in 2016 the wind farm started its commercial operation. In 2017 the wind farm produced 45.000 MWh of electricity, an equivalent to the electricity demand of 2.000 households.
Tyrinselkä wind farm consists of four Nordex N131 turbines, which have hub heights of 144 m and a total tip height of 210 m from ground level. The nominal power of one turbine is 3 MW, thus the electricity production total of the wind farm is 12 MW. The produced electricity is fed into the national grid through an own substation built next to the existing Caruna Oyj’s 110 kV grid lines. More than 60 landowners have been committed to the project and the project area covers more than 1000 ha of land.
Tyrinselkä wind farm was the most efficient wind farm in Finland with a capacity factor exceeding 43% in 2017.









